• Service Categories
  • Holloway Consulting’s hospital and medical facility projects.

    Folsom Prison, California
    Tehachapi Prison, California
    Vista County Jail, California
    Milpitas Correctional Facility, California
    Richard J. Donavan Prison, California
    Bakersfield (California) Memorial Hospital
    USC Medical Center, California
    Motion Picture and Television Fund Hospital, Calabasas, California
    Aurora Medical Center, Colorado
    Children’s Hospital, Colorado
    Yuma County Jail, Wray, Colorado
    Custer County Jail, Westcliff, Colorado
    Central Police and Fire Station, Loveland, Colorado
    Federal Correctional Complex, Florence, Colorado
    East Canon City Prison Project, Colorado
    Trinidad Correctional Facility, Trinidad, Colorado
    Arapahoe County Detention Facility, Colorado
    University of Massachusetts Memorial Medical Center
    County Sheriff’s Office and Detention Center, Nebraska
    Crawford County Justice Center, Ohio
    SABAH Annex Hospitals, Kuwait

    University of Massachusetts Memorial Medical Center

    When faced with delay claims from the general contractor, the University hired Holloway Consulting to perform an objective analysis of the issues. We concluded that the architect failed to comply with the standard of care and that the drawings submitted during the project did not contain the level of detail necessary to complete the project, which caused the estimate for cost of millwork and casework to be fifty percent off the final cost. We also found that the deficient design did not allow the University to evaluate potential project scope changes in light of the 30% difference in cost per square foot between the architect’s cost estimate and the final cost, and that these causes damaged University in the form of  delayed project completion and increased project costs, including change orders.

    University of Colorado Hospital/Anschutz Center for Advanced Medicine, Colorado

    Audits were typically conducted near the beginning of the project and upon project completion. Additionally, some of the larger projects included interim audits during construction. The typical audit scope for each project included:

    a) An assessment of the projected project cost versus budget;

    b) Review and documentation of the general contractor, architect and subcontractor selection processes;

    c) Assessment of the project controls and inspections processes being used by the project management team and architect;

    d) Review of the architect and general contractor payment applications to ensure that all billings included only allowable costs under the appropriate contracts; were supported by appropriate documentation; and were consistent with the progress of the work.

    e) Review of the subcontractor payment process, including confirming lien releases were obtained prior to payment, subcontractor billings to the general contractor conformed to their contracts, and an assessment of the timeliness of payments by the general contractor to the subcontractors.

    f) Assessment of General Conditions costs to date versus budget and the potential challenges for meeting that budget.

    g) Review and assessment of the project schedule, identifying any problem areas to date, the actions taken to address those problems, and the potential challenges for meeting that schedule.

    h) Review of the quality control processes conducted by the project management team, including architect inspections and materials testing, to identify any problems encountered and to document the actions taken to address those problem areas.

    St. Charles Hospital, New Orleans

    Steve Holloway was a member of the G/C’s staff on this project.

    Bakersfield (California) Memorial Hospital

    Steve Holloway was a member of the G/C’s staff on this project.

    USC Medical Center, California

    Steve Holloway was a member of the G/C’s staff on this project.

    Motion Picture and Television Fund Hospital, Calabasas, California

    Steve Holloway was a member of the G/C’s staff on this project.

    SABAH Annex Hospitals, Kuwait

     

    Aurora Medical Center, Colorado

     

    Children’s Hospital, Denver

    Use this Search Engine to find the terms and information you need at our site.

    And, the right side bar of each page here contains many related articles and posts.

    The Holloway Consulting Group, LLC
    Construction Advisers, Managers and Experts<
    12081 W. Alameda Pkwy., #450
    Lakewood, CO 80228-2701
    Denver Phone: (303) 984-1941
    International Toll Free: (888) 545-0666
    Fax: (303) 716-0432

    Email: steve.holloway@disputesinconstruction.com
    Blog: disputesinconstruction.com
    Web: hcgexperts.com

    _________________________________________

    See Related Selected Pages at our site hcgexperts.com (2-12-12)




    Leave your comment: